Atlas Energy Solutions' (AESI) two wholly owned indirect subsidiaries entered into separate cost-reimbursement agreements with a leading frontier AI lab, alongside equipment purchase agreements, to support specific data-center projects, the company said Friday.
The agreements cover long-lead-time equipment and incremental power generation.
One agreement supports balance-of-plant equipment for Atlas' existing Caterpillar (CAT) generator orders, while the other supports an incremental 283 megawatts of Caterpillar power-generation equipment for the initial power ramp of a separate data-center project.
Atlas also entered into a purchase agreement for 328 MW of generating capacity for delivery in 2027 under its Global Framework Agreement with Caterpillar.
Atlas Energy Solutions shares were up 7.8% in premarket activity.